Minetek Water implemented a specialised tailings dam management solution for a gold mining operation in Queensland, Australia. The project featured a three 600/300 Evaporation System Package, specifically designed to handle the site’s water management needs within the tailings dam. With a total volume throughput of 405 cubic meters per hour (1,800 gallons per minute), the systems effectively reduced water levels, enhancing site safety and operational efficiency.
Location – Queensland, Australia
Industry – Gold Mining
Application – Tailings Dam Management
Product – 3 x 600/300 Evaporation System Package
Volume throughput – 405 m3/hour (1,800 GPM)