Brief
Minetek’s client required a complete system designed to manage water levels at their gold mine in Ghana, Africa
Challenge
This gold mine required this solution to be developed within a tight timeframe, moving from design approval to installation within 7 weeks.
Solution
Minetek delivered a complete solution including a 12 x mechanical water evaporators with 4 x pontoon-based pumping system. The skid mounted design enables the site to quickly deploy the evaporators at various locations on their site and manage tailings dam levels in all weather conditions.
Minetek also delivered a total electrical solution including a skid mounted Motor Control Centre (MCC), soft starters for both pumps and evaporators, an electrical & control cable package as well as a austomation control sytem and weather station.
The solution included Minetek’s patented Environmental Management System (EMS), overall system, design, engineering, freight and onsite commissioning & training by our expert team.